Stadium Park Pool, Sunderland
Client: Balfour Beatty Construction Ltd
Value: £3.0 million
A contract for client Balfour Beatty Construction to provide the civils element of the North East's first 50m swimming pool, adjacent to the Stadium of Light.
The project entailed the excavation & construction of reinforced concrete bases and a water tight pool built to Olympic standards, as well as the construction of reinforced concrete diving boards.
Work also included the construction of foundations for a 'Wellness Centre', which will be used to treat visitors, and associated M&E and drainage works.
The two main project challenges were:
- Very tight construction tolerances
- Construction Sequence
Due to the tight construction sequence and extensive concrete works, programming was critical to the success of the project.
Tight specification and construction tolerances of +/- 3mm impose critical time periods between adjacent pours. This prevents cracking of the watertight structure. Restrictions require around three to seven days between adjacent concrete pours.
There was a total of 530 pours on the project, with around 3 pours per day.
On completion of the main civils works, water testing of the structures was completed over a period of several weeks.